Insights · 03 — Regulation

The sub-75MW advantage.

Texas Senate Bill 6 drew a regulatory line at 75MW. Which side of that line a site sits on now shapes its interconnection path, its obligations, and its timeline.

What SB6 did

Enacted in 2025, SB6 created a formal framework for large loads — 75MW and above — connecting to the ERCOT grid. Loads over the threshold face additional interconnection requirements: enhanced study and disclosure obligations, transmission screening, provisions for curtailment during grid emergencies, and cost-allocation rules designed to protect other ratepayers from stranded infrastructure.

The intent is sound — Texas is absorbing unprecedented load growth and the grid needs protecting. But the practical effect for developers is that the 75MW line is now a regulatory boundary with real schedule consequences on the far side.

What staying under it means

A site engineered below the threshold interconnects at the distribution level under standard utility processes — no large-load framework and no transmission queue. Sites take standard utility service — including the same firm-load-shed procedures that apply to all Texas load; what they avoid is the additional SB6 large-load curtailment and disclosure regime. The utility studies the load against existing distribution capacity and connects it. That's the structural basis for TPDS's 8–12 week modular delivery window.

Two sides of the line
Sub-75MW · distribution
Standard utility interconnection process
No transmission queue position required
Outside the SB6 large-load framework
Months to energization
75MW+ · large load
Enhanced study & disclosure obligations
Transmission screening and queue exposure
SB6 last-resort curtailment provisions (post-2025 large loads)
Years to energization

Deliberately sized, not capped

Sub-75MW is a product decision, not a ceiling on ambition. Each TPDS site energizes at 35MW with civil work, containment and transformer iron pre-engineered for expansion — and a portfolio of right-sized sites, linked by metro dark fiber where a tenant wants it, serves workloads that scale across sites rather than inside one fence line. Distributed by design. See the portfolio →

This page summarizes regulatory context in general terms and is not legal advice. Requirements evolve — the 75MW threshold is set by statute and implemented by the PUCT, which retains authority to adjust it — and treatment of any specific site and load is confirmed in diligence.